Introduction

The Town of West Bridgewater seeks solutions to address the growing demand for classroom space by building a new school or renovating and expanding existing facilities. The increase in the number of homes and apartments being built in town is projected to add over 25% in student population, primarily impacting the elementary schools. The total grades K through 6 enrollment reported by the District for the 2022-2023 school year was 725 students.

As a result of the analysis conducted on the base enrollment forecast and the historical enrollment trends of the District, the Massachusetts School Building Authority recommends the following projected enrollment for planning the proposed project:

  • Grades 1 through 3: 455 students
  • Grades K through 4: 750 students (plus pre-K students)
  • Grades 1 through 6: 930 students
  • Grades K through 6: 1,075 students (plus pre-K students)

Project objectives include the identification of community concerns that may impact potential options, as well as specific milestone requirements or constraints for the District. Alternative sites will be considered as well as the evaluation of the life cycle costs of operating the school in relation to future operational budgets. Other factors include the Northeast Collaborative for High Performance Schools (NE-CHPS) criteria or the US Green Building Council’s LEED for Schools (LEED-SJ) Rating System. The CM-at-Risk delivery method will also be explored as part of the process. The estimated total project costs of an approved project may range from $100,000,000 to $200,000,000.

Potential school consolidation focuses on the priority school, the Rose L MacDonald School which is serves grades 1-3 and the Spring Street School which houses grades PreK-K and the Central Office Staff.

Rose L MacDonald School

Rose L. MacDonald

Construction and Structure
This 39,000-SF single-story school was built in 1968 on 27.41 acres to house grades 1-3. It is a slab-on-grade brick masonry structure with single-pane windows with double insulation and a rubber membrane roof with skylights. The soffits are deteriorating, allowing wildlife and insects to enter the building. The roof has experienced leaks and the skylights are failing.

Condition and Maintenance
Maintenance staff actively addresses issues, but the building shows its age, especially in infrastructure and lack of modern educational amenities. The hallways have gradual ramps due to elevation changes.

Location
The school is isolated from other town schools, located over a mile away in a densely wooded residential area. It is accessible only by a narrow, winding road, creating traffic issues for buses and other vehicles.

Security and Safety Concerns
The isolated location and low roofline contribute to frequent vandalism, such as graffiti and broken windows and skylights. Some security cameras have been installed, but video coverage is insufficient for the entire site. The narrow driveway can become obstructed by fallen trees, which impede access for emergency responders. Traffic congestion at arrival/dismissal creates safety risks, resulting in minor accidents.

Athletic facilities
The gym is used by a youth athletic organization but is better suited for younger students only.

Howard School

Howard School

Construction and Site
Howard School was built in 1958 on 15.93 acres, houses grades 4-6, and includes the Town Library, a town playground (Friendship Park) and two soccer fields. In 1993, an 8,000-SF addition was built to accommodate the library, an administrative office, and a new entrance.

Building Layout
The school is a single-story building with two hallways leading from the main entry. The main entry includes the main office, nurse’s area, guidance room, cafeteria, and library. The classrooms are divided by grade: 4th grade in one wing, 6th grade in another, and 5th grade split between both wings, which is not ideal. Other spaces dedicated to specialists, related services, and special education move frequently due to changing enrollments.

Site Usage and Traffic
Howard School is located near the Spring Street School and the Middle/Senior High School; the Rose L. MacDonald School is over a mile away. The school shares its site with the Council on Aging building. Traffic issues arise from the shared parking lots and driveways.
A bus lane was added behind the school; student arrivals come through the main front door, using two doors for arrival/dismissal, contrary to safety preferences. Increased student enrollment and parent drop-offs cause traffic backups, especially during arrival and dismissal.
Youth athletic programs use the school facilities after instructional hours, although the gym is better suited for younger students.

Structural Issues
Salt treatment at entrances and at the loading dock has caused deterioration of the first course of exterior block walls. Septic lines and drains break through concrete floors due to settling in the building causes. Entrance door mullions cannot be removed for deliveries; doors have gaps, are not weather-tight, and weatherization strips impede closure. The VCT tile and cafeteria floor need replacement.

Maintenance and Support
Maintenance staff work diligently to address issues, but the building struggles to meet modern academic needs. The roof was replaced in 2018, but other maintenance challenges persist.

Security and Safety Concerns
Traffic congestion at arrival and dismissal poses safety risks; the School Resource Officer and police prefer using only one door for security. Outdoor security cameras have been added to improve visibility.

Spring Street School

Spring Street School

Construction and Renovations
Spring Street School is a 28,000-SF building constructed in 1956 which underwent significant updates in 1994-1995. The windows and frames were replaced and 40% of the flooring was replaced with vinyl tile, 60% with carpet. The bathrooms were renovated for ADA compliance, and a new hot water system and 5 new boilers were installed.

Building Layout
Spring Street School is divided into three pods. The school office, the nurse’s office, and the cafeteria are located in the first pod. The second pod consists of kindergarten classrooms. The third pod houses the preschool program and the central office for the district, e.g. Superintendent, Director of Student Services, the Business Office, and the Director of Curriculum. The pods were originally open but are now connected by long hallways. There are two entrances, one for the school and one for the central office area. There is a fenced recess area in the center of the building.

Location and Surroundings
Spring Street School is adjacent to the Middle/Senior High School and surrounded by residential homes. The parking area is shared with the Middle/Senior High School, creating traffic and safety concerns during arrival/dismissal due to bus and parent pick-up congestion.

Site and Drainage Issues
The site has poor drainage and holds water after heavy rain and snowmelt. The roof drainage system runs underground through cast iron pipes into stone leaching areas.

Security and Safety Concerns
The constant student drop-offs for grades 7-12 in the Spring Street School parking lot during the morning create additional congestion. Shared parking lot contributes to safety risks with buses and parent traffic at arrival and dismissal times. A separate entrance/exit for Spring Street School would reduce safety concerns caused by Middle/Senior High School traffic.