FAQs

The Level Principal plan starts with a higher payment, estimated at $310 per $100,000 of assessed value.  This payment then decreases every single year for the 30-year bond.

The Level Debt plan is more like a fixed-rate mortgage; it’s the same payment every year, estimated at $246.

The town’s anticipated plan is to use Level Principal because it saves the town a significant amount in total interest. The total payments for the Level Principal plan are about $12.6 million less than the Level Debt plan over the 30 years. It’s a trade-off: higher initial payments in exchange for substantial long-term savings for the town.

  • The $96 million for repairs is an estimate to fix the existing Rose L. MacDonald and Howard schools. That $96 million would be paid 100% by the town, with no state funding.
  • The $97.5 million for the new school is the town’s share after receiving an estimated $72.1 million grant from the state.

The most important distinction, is that the $96 million in repairs does not solve the core issues. It does not add needed classrooms , does not provide space for our projected enrollment , does not provide adequate special education spaces , and does not fix the inefficient layouts.

So, the choice is between spending $96 million to keep two old, undersized buildings, or spending $97.5 million for a brand new facility, funded in large part by the state, that is built to meet our students’ needs for the next 50 years.

The MSBA required the town to study all its options and present the single, most educationally and financially responsible solution for the district.

The WB School Building Committee, which is made up of West Bridgewater residents, parents, and town officials, studied smaller potential projects.

On April 8, 2025, the committee voted to proceed with this K-6 plan for three main reasons:

  1. It meets the district’s complete educational plan for all students.
  2. It is the only option that resolves all of the district’s needs for our elementary students.
  3. It maximizes the amount of the state grant.

Because this K-6 plan was the solution the building committee decided was most appropriate to meet the needs of the town AND officially submitted, it is now the only project the MSBA will co-fund.

  • The plan would open the Howard School for potential other uses. A new elementary school consolidates our K-6 students, which means the Howard School building would be available for the town to decide its next purpose.
  • This project also improves the Pre-K space in the Spring Street School. By moving all K-6 students to the new facility, we can better utilize Spring Street to serve our Pre-K population.

The $72 million grant is a reimbursement tied only to this specific new construction project, which the MSBA has approved as an educationally sound plan. Their funds are specifically for new construction or large-scale renovations that create modern educational facilities. They do not offer grants for general repairs on aging buildings.

If the town votes not to proceed with this project, that $72 million in state funding is forfeited and cannot be used for any other purpose.

  • First, this site moves all elementary traffic away from the center of town and the busy intersections at Routes 106 and 28.
  • The on-site loop is designed to queue up to 90 cars , and it separates bus and parent drop-off lanes. The goal of this design is to keep the parent line on the school site and prevent it from backing up onto North Elm Street.
  • To address North Elm Street directly, the project includes adding new left and right turn lanes from Steppingstone Drive onto North Elm, which helps keep traffic moving.
  • The plan also includes straightening and widening Steppingstone Drive  itself.

The building is designed as two distinct “schools” within one.

  • As you can see on the main floor plan , there is a “Lower school” for grades K-3 in one part of the building.
  • There is a separate “Upper school” for grades 4-6 in another.

These grade-level wings have their own classrooms, special education spaces, and extended learning commons . This design allows students to stay within their own age-appropriate area for most of the day, creating that small, supportive environment, while still benefiting from the modern, shared spaces like the gym, cafeteria, and library.

The MSBA is funded through one penny of the State’s 6.25% sales tax. Each year, the MSBA receives selects a limited number of applicants to be invited into its Core program.

The projected base reimbursement rate is 54.79% plus (0-2%) maintenance incentive and up to 4% additional potential reimbursement based on energy efficiency.  Reimbursement applies to ‘eligible’ project costs only.  Examples of ineligible costs include abatement of vinyl asbestos tile, moving costs, swing space, soft costs in excess of 20% of construction cost, site costs in excess of $59/SF, and building costs in excess of $586/SF.  Projected ineligible scope will be factored into the projected district share.

The MSBA Accelerated Repair Program is for the partial or full replacement of roofs, windows/doors and/or boilers. The MSBA Core Program would be for repairs above and beyond those listed in the accelerated repair program. The Rose L. MacDonald School with the consolidation of the Howard School and Spring Street School, has been invited to participate in the MSBA Core Program.

Rose L. Macdonald school is a 39,000-SF single-story school that was built in 1968 on 27.41 acres to house grades 1-3. It is a slab-on-grade brick masonry structure with single-pane windows with double insulation and a rubber membrane roof with skylights. The soffits are deteriorating, allowing wildlife and insects to enter the building. The roof has experienced leaks and the skylights are failing.

 

Howard School is a 45,000-SF building built in 1958 on 15.93 acres, houses grades 4-6, and includes the Town Library, a town playground (Friendship Park) and two soccer fields. In 1993, an 8,000-SF addition was built to accommodate the library, an administrative office, and a new entrance.

 

Spring Street School is a 28,000-SF building constructed in 1956 which underwent significant updates in 1994-1995. The windows and frames were replaced and 40% of the flooring was replaced with vinyl tile, 60% with carpet. The bathrooms were renovated for ADA compliance, and a new hot water system and 5 new boilers were installed.

Below are the enrollment and configuration options as a result of a collaborative analysis with the MSBA prior to commencement of the feasibility study.

 

Grades 1-3 (at Rose L MacDonald), 455 Students

Grades K-4 (consolidation with Spring Street and Howard), 750 Students (plus pre-k)

Grades 1-6 (consolidation with Howard), 930 Students

Grades K-6 (consolidation with Spring Street and Howard), 1075 Students (plus pre-k)

The Owner’s Project Manager (OPM) provides project management services to the Owner throughout the life of the Project. Consequently, the owner will work closely with the OPM from the earliest stages of the project through to the completion of the project. The selection of a qualified OPM is one of the most important decisions an Owner will make for the project as the OPM has extensive experience on MSBA projects. In the (insert date/time frame), the School Building Committee formed a Procurement Subcommittee. It was this committee’s responsibility to follow the MSBA’s defined process to select the OPM and to recommend an OPM to the full School Building Committee which, in turn, recommended our selection to the MSBA Owner’s Project Manager Selection Panel. On May 06th, 2024, the MSBA approved our selection of PMA as our Owner’s Project Manager. After this approval, the Board of Selectman authorized the execution of the contract for services with PMA.

The Designer is primarily responsible for working with the District to complete all the objectives outlined in the Feasibility and Schematic Design phase of the project. The selection of a Designer must follow a specific process as outlined by the MSBA. The MSBA Designer Selection Panel (DSP) has jurisdiction over the procurement of designers. The DSP includes 13 representatives appointed by the MSBA and 3 representatives from the Town.  At the MSBA’s Designer Selection Panel meeting on August 27th, 2024, HMFH Architects was selected as the Designer for the Town of West Bridgewater. The contract with HMFH Architects was authorized for execution by the Town Administrator on September 27th, 2024.

During the study process, the SBC and project team considered multiple sites throughout the town.  Strong consideration was given to the Spring St, Howard Street and Rose L. sites.  Ultimately the SBC decided to move forward with the Rose L. MacDonald site as the most viable site for a new school project.

 

At both the Spring Street and Howard Street sites, adding any capacity to the existing septic system would trigger the need for a wastewater treatment plant (WWTP) sized to serve most of the town buildings. Given the site constraints, neither site could accommodate a WWTP onsite. At the time of site selection there were no offsite properties available for a WWTP.  Additionally, the Spring Street site is too small to accommodate a larger building, and the existing building would have needed to be demolished prior to the construction of a new building requiring temporary classroom space located elsewhere. The Howard Street site also has limited space, multiple other on-site and adjacent buildings, making for a congested site paired with the need to construct a WWTP made the site non-viable.

Yes, there will be a buffer. Through the design, the project team is maintaining a setback from the Goldie Road abutters to the new school.

Since the MSHS was built the overall cost of building has increased. You can find a detailed chart on these costs on the MSBA website (https://info.massschoolbuildings.org/TabPub/TableauCostData.aspx).

Using the above chart, in 2014, the cost of construction was roughly $300/SF. Looking at 2025, the costs of construction is roughly $900/SF.

The project team will continue to work on the Schematic Design package which is due to the MSBA on October 23, 2025.

When school returns in September, the project team will attend open houses and other school activities to answer any questions about the new school project. The project team will host additional community forums in advance of the town vote to approve the project funding.

The town vote will take place in January 2026 (exact date TBD).

The grade configuration for the new school at the Rose L. MacDonald Site will be Grades K-6 with an enrollment of 1075. This grade configuration will combine the existing Rose L. MacDonald, Howard Street and Kindergarten from Spring Street into one location. The PreK is currently planned to stay at the Spring Street school, but the Town will investigate any costs associated with updates at Spring Street or the possibility of moving PreK to the Howard School at some point. The location of PreK will ultimately be up to the School Committee.